USFWS-IWW-06

Dewatering/Diversion

The area to be dewatered will encompass the minimum area necessary to perform construction activities. The Project Proponent will provide a dewatering plan with a description of the proposed dewatering structures and appropriate BMPs for the installation, operation, maintenance, and removal of those structures. The period of dewatering/diversion will extend only for the minimum amount of time needed to perform the restoration activity and to allow Covered Species time to leave on their own before final clearance surveys and construction can begin. Dewatering/diversion will occur via gravity-driven systems, where feasible and except as specified below. Dewatering/diversion will be designed to avoid direct and preventable indirect mortality of fish and other aquatic species. If Covered Fish Species may be present in the area to be dewatered, a fish capture and relocation plan will be developed and implemented for review and approval by the appropriate agencies. Stream flows will be allowed to gravity flow around or through the work site, using temporary bypass pipes or culverts. Bypass pipes will be sized to accommodate a minimum of twice the expected construction-period flow and not increase stream velocity and will be placed at stream grade. Conveyance pipe outlet energy dissipaters will be installed to prevent scour and turbidity at the discharge location.

When gravity-fed dewatering is not feasible and pumping is necessary to dewater a work site, a temporary siltation basin and/or silt bags may be required to prevent sediment from reentering the wetted channel. Silt fences or mechanisms to avoid sediment input to the flowing channel will be installed adjacent to flowing water. Water pumped or removed from dewatered areas will be conducted in a manner that does not contribute turbidity to nearby receiving waters. Pumps will be refueled in an area well away from the stream channel. Fuel-absorbent mats will be placed under the pumps while refueling. Equipment working in the stream channel or within 25 feet of a wetted channel will have a double (i.e., primary and secondary) containment system for diesel and oil fluids.

All work will comply with the CDFW Fish Screening Criteria (CDFW 2001) or NMFS Fish Screening Criteria for Anadromous Salmonids (NOAA 2022). Pump intakes will be covered with mesh, in accordance with the requirements of current fish screening criteria, to prevent potential entrainment of fish or other aquatic species that could not be removed from the area to be dewatered. The pump intake will be checked periodically for impingement of fish or other aquatic species. Diverted flows must be of sufficient quality and quantity, and of appropriate temperature, to support existing fish and other aquatic life both above and below the diversion. Pre-project flows must be restored to the affected surface waterbody on completion of work at that location. Where diversions are planned, contingency plans will be developed that include oversight for breakdowns, fueling, maintenance, leaks, etc.