SWRCB-REP-01

Pre-Construction Survey

An agency-approved biologist will conduct preconstruction surveys for the target reptile species within 72 hours prior to any initial ground disturbance within all suitable habitat within or adjacent to the project site and accessible to the project proponent, to identify locations where special-status reptiles may be present, evaluate current activity status in the project area, and protect the species and its habitat from avoidable construction-related disturbance. The intent of this survey is to assess current special-status reptile habitat and use locations in the project area immediately prior to construction. Preconstruction surveys may be phased across a construction site if construction in different areas will occur at different times; only areas where disturbance is imminent need be surveyed. The project area will be re-inspected by the agency-approved biologist whenever a lapse in construction activity of 5 days or greater has occurred.