USFWS-VHDR-05

Revegetation Monitoring and Reporting

All revegetated areas will be maintained and monitored for a minimum of 2 years after replanting is complete, or until success criteria are met, to ensure that the revegetation effort is successful. The standard for success is 60% cover compared to pre-project conditions at the project site or at least 60% cover compared to an intact, local reference site. If an appropriate reference site or pre-project conditions cannot be identified, success criteria will be developed for review and approval on a project-by-project basis, based on the specific habitat impacted and known recovery times for that habitat and geography. The Project Proponent will prepare a summary report of the monitoring results and recommendations on December 1 each year. The report will be provided to the respective USFWS Field Office (copy the Lead Action Agency).